Construction Sequence
Stage 1
Day 1 Morning - Dig foundation holes
Day 1 Afternoon- Pour Concrete - Set Piers
Day 2 - Morning - Assemble Sub Floor
Day 2 - Afternoon - Lay Floor
Day 3 - Assemble & Stand Frames